Gokul Paradise, Goregaon West
by Shree Radhe Construction · Goregaon West, Mumbai 400104 · Map
- Launched
- Feb 20222 yrs 10 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 3 yrs
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 3 of 1127% · 22 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale3 booked out of 11 units
Rehab22 units for existing members
Total 33 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 20
- 2 BHK
- 13
- Total units
- 33
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 11
- Rehab units
- 22
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 3 | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400104
Projects with 10–70 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 10 mths | 3 yrs 3 mths |
| Possession date extended | By 3 yrs | 2 of 3 |
| Possession date (MahaRERA) | Dec 2027 | Nov 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 27% | 80% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Diyana Villa, Goregaon West
- Shastri Nagar Prabhat Chsl Phase II A And B Wing, Goregaon West
- Paras Residency, Goregaon West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Diyana Villa | February 2022 | December 2029 | 100% | 21 units booked out of 21 units for sale |
| Shastri Nagar Prabhat Chsl Phase II A And B Wing | March 2022 | December 2025 | 0% | 20 units booked out of total 25 units |
| Paras Residency | June 2022 | November 2026 | 100% | 6 units booked out of 22 units for sale |
About this project
Gokul Paradise by Shree Radhe Construction is a 33-unit BMC-sanctioned project in Goregaon West, Mumbai 400104, launched in February 2022 with possession due in December 2027. 3 units booked out of 11 units for sale. The concrete structure (RCC) is complete.
Read full summary
Gokul Paradise is a BMC-sanctioned project by Shree Radhe Construction in Goregaon West, Mumbai 400104, registered with MahaRERA as P51800033025. It was launched in February 2022. It has 33 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 33 units, 11 are for sale and 22 are rehab units for existing members.
Its registered possession date is December 2027, extended by 3 years from the original December 2024. Construction: excavation complete, structure (RCC) complete, final finishes not started.
3 units booked out of 11 units for sale (27%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 100%.