Samarth Aura, Bhandup West
by Shree Ashapura Combine · Bhandup West, Mumbai 400078 · Map
- Launched
- Feb 2022First of 2 phases
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Weighted across 2 phases
- Booked
- 157 of 16893%
- Buildings
- 20.9 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 40
- 2 BHK
- 88
- 3 BHK
- 40
- Total units
- 168
- Buildings
- 2
- Land
- 0.9 acres
- Phases
- 2
- MahaRERA complaints
- 1
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Samarth Aura Phase -1 Nearing possession | P51800033159 | 84 | 100% | 99% | |
| Samarth Aura Phase -2 Completed | P51800050555 | 84 | 100% | 88% |
Show updates by phase
Samarth Aura Phase -1 (P51800033159)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 20% | 83 | |
| 100% | 100% | 20% | 83 | |
| 100% | 100% | 20% | 83 | |
| 100% | 24% | 0% | 68 |
"–" means MahaRERA shows no figure for that update.
Samarth Aura Phase -2 (P51800050555)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 74 | |
| 100% | 100% | 100% | 74 | |
| 100% | 100% | 65% | 71 | |
| 100% | 0% | 0% | 6 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Compared with 4 similar projects in PIN 400078
Projects with 80–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 9 mths | 5 yrs 2 mths |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | Dec 2026 | Dec 2026 |
| Concrete structure (RCC) | 100% | 69% |
| Units booked | 93% | 41% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 4 projects
- Shraddha Prime, Bhandup West
- Dream Olympia, Bhandup West
- Ganesh Bhuvan CHS Ltd, Bhandup West
- Sai Akshi, Bhandup West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shraddha Prime | March 2022 | December 2025 | 100% | 28 units booked out of total 114 units |
| Dream Olympia | January 2022 | December 2026 | 30% | 21 units booked out of total 103 units |
| Ganesh Bhuvan CHS Ltd | December 2021 | December 2027 | 88% | 192 units booked out of 192 units for sale |
| Sai Akshi | August 2021 | December 2026 | 50% | 102 units booked out of total 176 units |
About this project
Samarth Aura by Shree Ashapura Combine is a 168-unit BMC-sanctioned project in Bhandup West, Mumbai 400078, registered with MahaRERA in 2 phases, with possession due in December 2026. 157 units booked out of total 168 units. The concrete structure (RCC) is complete.
Read full summary
Samarth Aura is a BMC-sanctioned project by Shree Ashapura Combine in Bhandup West, Mumbai 400078, registered with MahaRERA as 2 phases (P51800033159, P51800050555). The first phase was launched in February 2022. Together the phases have 168 units in 2 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. On MahaRERA, 1 is active and 1 is completed.
The registered possession date is December 2026; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 60% complete. Both phases have their structure complete.
157 units booked out of total 168 units (93%).