Samarth Aura, Bhandup West

by Shree Ashapura Combine · Bhandup West, Mumbai 400078 · Map

Launched
Feb 2022First of 2 phases
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Weighted across 2 phases
Booked
157 of 16893%
Buildings
20.9 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
40
2 BHK
88
3 BHK
40
Total units
168
Buildings
2
Land
0.9 acres
Phases
2
MahaRERA complaints
1

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Samarth Aura Phase -1
Nearing possession
P5180003315984100%99%
Samarth Aura Phase -2
Completed
P5180005055584100%88%
Show updates by phase

Samarth Aura Phase -1 (P51800033159)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%20%83
100%100%20%83
100%100%20%83
100%24%0%68

"–" means MahaRERA shows no figure for that update.

Samarth Aura Phase -2 (P51800050555)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%74
100%100%100%74
100%100%65%71
100%0%0%6

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 12%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 43%Jul 2026: Final finishes 60%Oct 2026: Final finishes 60%Excavation 100%Concrete structure (RCC) 100%Final finishes 60%

How to read construction stages

Compared with 4 similar projects in PIN 400078

Projects with 80–350 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400078
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 9 mths5 yrs 2 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Dec 2026Dec 2026
Concrete structure (RCC)100%69%
Units booked93%41%
MahaRERA complaints (filed by or against the builder)10

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Samarth Aura by Shree Ashapura Combine is a 168-unit BMC-sanctioned project in Bhandup West, Mumbai 400078, registered with MahaRERA in 2 phases, with possession due in December 2026. 157 units booked out of total 168 units. The concrete structure (RCC) is complete.

Read full summary

Samarth Aura is a BMC-sanctioned project by Shree Ashapura Combine in Bhandup West, Mumbai 400078, registered with MahaRERA as 2 phases (P51800033159, P51800050555). The first phase was launched in February 2022. Together the phases have 168 units in 2 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. On MahaRERA, 1 is active and 1 is completed.

The registered possession date is December 2026; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 60% complete. Both phases have their structure complete.

157 units booked out of total 168 units (93%).