Sanghvi Parsssva Jivdaya, Ghatkopar West
by Sanghvi Constructions · Ghatkopar West, Mumbai 400086 · Map
- Launched
- Feb 20223 yrs 10 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 1 yr
- Concrete structure
- 90%Mid-construction
- Booked (free sale)
- 26 of 26100% · 23 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale26 booked out of 26 units
Rehab23 units for existing members
Total 49 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 45
- Other units
- 4
- Total units
- 49
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 26
- Rehab units
- 23
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 0% | 26 | |
| 100% | 80% | 0% | 20 | |
| 100% | 80% | 0% | 20 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Sanghvi Parsssva Jivdaya by Sanghvi Constructions is a 49-unit BMC-sanctioned project in Ghatkopar West, Mumbai 400086, launched in February 2022 with possession due in December 2026. 26 units booked out of 26 units for sale. The concrete structure (RCC) is 90% complete.
Read full summary
Sanghvi Parsssva Jivdaya is a BMC-sanctioned project by Sanghvi Constructions in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800033259. It was launched in February 2022. It has 49 units in 1 building: 45 homes (2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 49 units, 26 are for sale and 23 are rehab units for existing members.
Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) 90% complete, final finishes not started.
26 units booked out of 26 units for sale (100%). Since the July 2026 update, 6 more units have been booked and the reported concrete structure (RCC) has gone from 80% to 90%.