Monte Verita West Tower, Borivali East

by B G Shirke Redevelopment and GAS P L · Borivali East, Mumbai 400066 · Map

Launched
Feb 20225 yrs 1 mth promised
Possession (MahaRERA)
Mar 2027Not extended
Concrete structure
0%Early stage
Booked
–
Buildings
10.6 acres
MahaRERA complaints
5Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Total units
–
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
5

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%–
100%0%0%–
100%0%0%88

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Monte Verita West Tower by B G Shirke Redevelopment and GAS P L is a project in Borivali East, Mumbai 400066, launched in February 2022 with possession due in March 2027. Work on the concrete structure (RCC) has not started.

Read full summary

Monte Verita West Tower is a project by B G Shirke Redevelopment and GAS P L in Borivali East, Mumbai 400066, registered with MahaRERA as P51800033312. It was launched in February 2022. Its MahaRERA status is Active.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.