Pratap Vista, Andheri East
by Parnakutir Real Estate Pvt Ltd · Andheri East, Mumbai 400069 · Map
- Launched
- Mar 20223 yrs 9 mths originally promised
- Possession (MahaRERA)
- Jun 2028Extended by 2 yrs 6 mths
- Concrete structure
- 10%Mid-construction
- Booked (free sale)
- 9 of 1275% · 10 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale9 booked out of 12 units
Rehab10 units for existing members
Total 22 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 14
- 2 BHK
- 3
- Other units
- 5
- Total units
- 22
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 12
- Rehab units
- 10
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 10% | 0% | 9 | |
| 100% | 10% | 0% | 9 | |
| 100% | 10% | 0% | – | |
| 100% | 10% | 0% | 10 |
"–" means MahaRERA shows no figure for that update.
About this project
Pratap Vista by Parnakutir Real Estate Pvt Ltd is a 22-unit BMC-sanctioned project in Andheri East, Mumbai 400069, launched in March 2022 with possession due in June 2028. 9 units booked out of 12 units for sale. The concrete structure (RCC) is 10% complete.
Read full summary
Pratap Vista is a BMC-sanctioned project by Parnakutir Real Estate Pvt Ltd in Andheri East, Mumbai 400069, registered with MahaRERA as P51800034213. It was launched in March 2022. It has 22 units in 1 building: 17 homes (1 and 2 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 22 units, 12 are for sale and 10 are rehab units for existing members.
Its registered possession date is June 2028, extended by 2 years 6 months from the original December 2025. Construction: excavation complete, structure (RCC) 10% complete, final finishes not started.
9 units booked out of 12 units for sale (75%).