Kalpataru Vivant - South, Jogeshwari East
by Alder Residency Private Limited · Jogeshwari East, Mumbai 400060 · Map
- Launched
- Apr 2022First of 4 phases
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 99%Weighted across 4 phases
- Booked
- 318 of 33695% · 289 in Jul 2026
- Buildings
- 40.1 acres
- MahaRERA complaints
- 3Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 210
- 2 BHK
- 126
- Total units
- 336
- Buildings
- 4
- Land
- 0.1 acres
- Phases
- 4
- MahaRERA complaints
- 3
The 4 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Kalpataru Vivant - South Wing B Completed | P51800034531 | 86 | 100% | 99% | |
| Kalpataru Vivant - South Wing A Completed | P51800045360 | 86 | 100% | 99% | |
| Kalpataru Vivant - South Wing C Nearing possession | P51800053558 | 82 | 100% | 98% | |
| Kalpataru Vivant - South Wing E Mid-construction | P51800053828 | 82 | 97% | 83% |
Show updates by phase
Kalpataru Vivant - South Wing B (P51800034531)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 80% | 85 | |
| 100% | 100% | 80% | 85 | |
| 100% | 100% | 47% | 82 | |
| 100% | 100% | 4% | 62 |
"–" means MahaRERA shows no figure for that update.
Kalpataru Vivant - South Wing A (P51800045360)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 85 | |
| 100% | 100% | 95% | 85 | |
| 100% | 100% | 47% | 77 | |
| 100% | 100% | 11% | 58 |
"–" means MahaRERA shows no figure for that update.
Kalpataru Vivant - South Wing C (P51800053558)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 35% | 80 | |
| 100% | 100% | 4% | 63 | |
| 97% | 52% | 1% | 41 | |
| 97% | 10% | 1% | 27 |
"–" means MahaRERA shows no figure for that update.
Kalpataru Vivant - South Wing E (P51800053828)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 97% | 3% | 68 | |
| 100% | 85% | 1% | 56 | |
| 100% | 52% | 1% | 33 | |
| 100% | 0% | 1% | 8 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Kalpataru Vivant - South by Alder Residency Private Limited (Kalpataru) is a 336-unit BMC-sanctioned project in Jogeshwari East, Mumbai 400060, registered with MahaRERA in 4 phases, with possession due in December 2028. 318 units booked out of total 336 units. The concrete structure (RCC) is 99% complete.
Read full summary
Kalpataru Vivant - South is a BMC-sanctioned project by Alder Residency Private Limited in Jogeshwari East, Mumbai 400060, registered with MahaRERA as 4 phases (P51800034531, P51800045360, P51800053558, P51800053828). The first phase was launched in April 2022. Together the phases have 336 units in 4 buildings, with 1 and 2 BHK homes as registered with MahaRERA. On MahaRERA, 2 are completed and 2 are active.
The registered possession date is December 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 99% complete and final finishes 54% complete. 3 of the 4 phases have their structure complete.
318 units booked out of total 336 units (95%). Since the July 2026 update, 29 more units have been booked.
Kalpataru's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 42 |
|---|---|
| Total units across these projects | 6,678 |
| Completed without extending the possession date | 19 |
| Completed after an extension | 8 |
| Lapsed | 0 |
| Under construction | 15 |
| Possession date extended on the builder's application | 9 |
| Typical time from launch to 100% structure | 5 years 10 months |
| MahaRERA complaints (filed by or against the builder), all Kalpataru projects | 225 (21 of 42 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.