Jangid Elysium, Borivali East

by Imprint Construction Private Limited · Borivali East, Mumbai 400066 · Map

Launched
Apr 20223 yrs 8 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 1 yr
Concrete structure
100%Nearing possession
Booked
439 of 45197%
Buildings
10.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
451
Total units
451
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%439
100%100%0%439
100%0%0%428
100%0%0%339

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Jangid Elysium by Imprint Construction Private Limited is a 451-unit SRA-sanctioned project in Borivali East, Mumbai 400066, launched in April 2022 with possession due in December 2026. 439 units booked out of total 451 units. The concrete structure (RCC) is complete.

Read full summary

Jangid Elysium is an SRA-sanctioned project by Imprint Construction Private Limited in Borivali East, Mumbai 400066, registered with MahaRERA as P51800034600. It was launched in April 2022. It has 451 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes not started.

439 units booked out of total 451 units (97%).