Elegance Heights, Malad East

by SGF Enterprises · Malad East, Mumbai 400097 · Map

Launched
Apr 20224 yrs 6 mths originally promised
Possession (MahaRERA)
Dec 2029Extended by 3 yrs 2 mths
Concrete structure
7%Mid-construction
Booked
3 of 2401% · 1 in Jul 2026
Buildings
10.7 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
28
2 BHK
196
Other units
16
Total units
240
Buildings
1
Land
0.7 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)7%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 7%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 7%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%7%0%3
100%0%0%1
100%0%0%–
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400097

Projects with 100–450 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400097
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 6 mths3 yrs 9 mths
Possession date extendedBy 3 yrs 2 mths2 of 3
Possession date (MahaRERA)Dec 2029Dec 2027
Concrete structure (RCC)7%75%
Units booked1%75%
MahaRERA complaints (filed by or against the builder)20

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Elegance Heights by SGF Enterprises is a 240-unit SRA-sanctioned project in Malad East, Mumbai 400097, launched in April 2022 with possession due in December 2029. 3 units booked out of total 240 units. The concrete structure (RCC) is 7% complete.

Read full summary

Elegance Heights is an SRA-sanctioned project by SGF Enterprises in Malad East, Mumbai 400097, registered with MahaRERA as P51800034810. It was launched in April 2022. It has 240 units in 1 building: 224 homes (1 and 2 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2029, extended by 3 years 2 months from the original October 2026. Construction: excavation complete, structure (RCC) 7% complete, final finishes not started.

3 units booked out of total 240 units (1%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 7%.