104 East, Goregaon East

by Quba Infra LLP · Goregaon East, Mumbai 400063 · Map

Launched
May 20222 yrs 7 mths originally promised
Possession (MahaRERA)
Oct 2027Extended by 2 yrs 10 mths
Concrete structure
90%Mid-construction
Booked
64 of 8873% · 78 in Jul 2026
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
88
Total units
88
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)90%
Finishes, lifts and services30%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 90%Dec 2025: Excavation 95%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 45%Dec 2025: Concrete structure (RCC) 45%Jul 2026: Concrete structure (RCC) 82%Oct 2026: Concrete structure (RCC) 90%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 15%Oct 2026: Final finishes 30%Excavation 100%Concrete structure (RCC) 90%Final finishes 30%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%30%64
100%82%15%78
95%45%0%–
90%45%0%16

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

104 East by Quba Infra LLP is an 88-unit BMC-sanctioned project in Goregaon East, Mumbai 400063, launched in May 2022 with possession due in October 2027. 64 units booked out of total 88 units. The concrete structure (RCC) is 90% complete.

Read full summary

104 East is a BMC-sanctioned project by Quba Infra LLP in Goregaon East, Mumbai 400063, registered with MahaRERA as P51800035079. It was launched in May 2022. It has 88 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is October 2027, extended by 2 years 10 months from the original December 2024. Construction: excavation complete, structure (RCC) 90% complete, final finishes 30% complete.

64 units booked out of total 88 units (73%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 82% to 90% and the possession date has moved from December 2025 to October 2027.