Greenairy, Borivali East
by Saroj Landmark Realty LLP · Borivali East, Mumbai 400066 · Map
- Launched
- May 20226 yrs 1 mth promised
- Possession (MahaRERA)
- Jun 2028Not extended
- Concrete structure
- 100%Nearing possession
- Booked
- 872 of 1,05283% · 858 in Jul 2026
- Buildings
- 21.1 acres
- MahaRERA complaints
- 8Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 296
- 2 BHK
- 562
- Other units
- 194
- Total units
- 1,052
- Buildings
- 2
- Land
- 1.1 acres
- Phases
- 1
- MahaRERA complaints
- 8
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 60% | 872 | |
| 0% | 0% | 0% | 858 | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | 659 |
"–" means MahaRERA shows no figure for that update.
About this project
Greenairy by Saroj Landmark Realty LLP is a 1,052-unit SRA-sanctioned project in Borivali East, Mumbai 400066, launched in May 2022 with possession due in June 2028. 872 units booked out of total 1,052 units. The concrete structure (RCC) is complete.
Read full summary
Greenairy is an SRA-sanctioned project by Saroj Landmark Realty LLP in Borivali East, Mumbai 400066, registered with MahaRERA as P51800035093. It was launched in May 2022. It has 1,052 units in 2 buildings: 858 homes (1 and 2 BHK) and 194 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete.
872 units booked out of total 1,052 units (83%). Since the July 2026 update, 14 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 100%.