Kalpataru Vivant - North, Jogeshwari East
by Alder Residency Private Limited · Jogeshwari East, Mumbai 400060 · Map
- Launched
- May 2022First of 6 phases
- Possession (MahaRERA)
- Dec 2028 – Jun 2029Not extended
- Concrete structure
- 100%Weighted across 6 phases
- Booked
- 579 of 64789% · 562 in Jul 2026
- Buildings
- 60.2 acres
- MahaRERA complaints
- 5Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 404
- 3 BHK
- 243
- Total units
- 647
- Buildings
- 6
- Land
- 0.2 acres
- Phases
- 6
- MahaRERA complaints
- 5
The 6 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Kalpataru Vivant - North Wing B Completed | P51800045409 | 102 | 100% | 94% | |
| Kalpataru Vivant - North Wing E Completed | P51800047620 | 100 | 100% | 97% | |
| Kalpataru Vivant - North Wing C Completed | P51800047621 | 122 | 100% | 79% | |
| Kalpataru Vivant - North Wing D Completed | P51800051153 | 118 | 100% | 90% | |
| Kalpataru Vivant - North Wing A Nearing possession | P51800051328 | 104 | 100% | 88% | |
| Kalpataru Vivant - North Wing F Mid-construction | P51800077538 | 101 | 97% | 92% |
Show updates by phase
Kalpataru Vivant - North Wing B (P51800045409)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 32% | 96 | |
| 100% | 100% | 32% | 96 | |
| 100% | 100% | 15% | 96 | |
| 100% | 97% | 5% | 95 |
"–" means MahaRERA shows no figure for that update.
Kalpataru Vivant - North Wing E (P51800047620)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 20% | 97 | |
| 100% | 100% | 20% | 97 | |
| 100% | 100% | 11% | 97 | |
| 100% | 63% | 3% | 96 |
"–" means MahaRERA shows no figure for that update.
Kalpataru Vivant - North Wing C (P51800047621)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 20% | 96 | |
| 100% | 100% | 20% | 96 | |
| 100% | 100% | 11% | 90 | |
| 100% | 68% | 2% | 84 |
"–" means MahaRERA shows no figure for that update.
Kalpataru Vivant - North Wing D (P51800051153)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 20% | 106 | |
| 100% | 100% | 20% | 106 | |
| 100% | 100% | 11% | 100 | |
| 100% | 63% | 2% | 91 |
"–" means MahaRERA shows no figure for that update.
Kalpataru Vivant - North Wing A (P51800051328)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 55% | 91 | |
| 100% | 100% | 50% | 78 | |
| 100% | 95% | 7% | 74 | |
| 100% | 0% | 0% | 65 |
"–" means MahaRERA shows no figure for that update.
Kalpataru Vivant - North Wing F (P51800077538)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 97% | 7% | 93 | |
| 100% | 80% | 5% | 89 | |
| 100% | 26% | 0% | 55 | |
| 94% | 0% | 0% | 20 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Kalpataru Vivant - North by Alder Residency Private Limited (Kalpataru) is a 647-unit BMC-sanctioned project in Jogeshwari East, Mumbai 400060, registered with MahaRERA in 6 phases, with possession dates from December 2028 to June 2029. 579 units booked out of total 647 units. The concrete structure (RCC) is complete.
Read full summary
Kalpataru Vivant - North is a BMC-sanctioned project by Alder Residency Private Limited in Jogeshwari East, Mumbai 400060, registered with MahaRERA as 6 phases (P51800045409, P51800047620, P51800047621, P51800051153, P51800051328, P51800077538). The first phase was launched in May 2022. Together the phases have 647 units in 6 buildings, with 2 and 3 BHK homes as registered with MahaRERA. On MahaRERA, 4 are completed and 2 are active.
The phases' registered possession dates run from December 2028 to June 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 25% complete. 5 of the 6 phases have their structure complete.
579 units booked out of total 647 units (89%). Since the July 2026 update, 17 more units have been booked.
Kalpataru's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 42 |
|---|---|
| Total units across these projects | 6,678 |
| Completed without extending the possession date | 19 |
| Completed after an extension | 8 |
| Lapsed | 0 |
| Under construction | 15 |
| Possession date extended on the builder's application | 9 |
| Typical time from launch to 100% structure | 5 years 10 months |
| MahaRERA complaints (filed by or against the builder), all Kalpataru projects | 225 (21 of 42 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.