Skip to main content

Kalpataru Vivant - North, Jogeshwari East

by Alder Residency Private Limited · Jogeshwari East, Mumbai 400060 · Map

Launched
May 2022First of 6 phases
Possession (MahaRERA)
Dec 2028 – Jun 2029Not extended
Concrete structure
100%Weighted across 6 phases
Booked
579 of 64789% · 562 in Jul 2026
Buildings
60.2 acres
MahaRERA complaints
5Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
404
3 BHK
243
Total units
647
Buildings
6
Land
0.2 acres
Phases
6
MahaRERA complaints
5

The 6 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Kalpataru Vivant - North Wing B
Completed
P51800045409102100%94%
Kalpataru Vivant - North Wing E
Completed
P51800047620100100%97%
Kalpataru Vivant - North Wing C
Completed
P51800047621122100%79%
Kalpataru Vivant - North Wing D
Completed
P51800051153118100%90%
Kalpataru Vivant - North Wing A
Nearing possession
P51800051328104100%88%
Kalpataru Vivant - North Wing F
Mid-construction
P5180007753810197%92%
Show updates by phase

Kalpataru Vivant - North Wing B (P51800045409)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%32%96
100%100%32%96
100%100%15%96
100%97%5%95

"–" means MahaRERA shows no figure for that update.

Kalpataru Vivant - North Wing E (P51800047620)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%20%97
100%100%20%97
100%100%11%97
100%63%3%96

"–" means MahaRERA shows no figure for that update.

Kalpataru Vivant - North Wing C (P51800047621)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%20%96
100%100%20%96
100%100%11%90
100%68%2%84

"–" means MahaRERA shows no figure for that update.

Kalpataru Vivant - North Wing D (P51800051153)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%20%106
100%100%20%106
100%100%11%100
100%63%2%91

"–" means MahaRERA shows no figure for that update.

Kalpataru Vivant - North Wing A (P51800051328)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%55%91
100%100%50%78
100%95%7%74
100%0%0%65

"–" means MahaRERA shows no figure for that update.

Kalpataru Vivant - North Wing F (P51800077538)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%97%7%93
100%80%5%89
100%26%0%55
94%0%0%20

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services25%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 99%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 49%Dec 2025: Concrete structure (RCC) 88%Jul 2026: Concrete structure (RCC) 97%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 2%Dec 2025: Final finishes 9%Jul 2026: Final finishes 24%Oct 2026: Final finishes 25%Excavation 100%Concrete structure (RCC) 100%Final finishes 25%

How to read construction stages

About this project

Kalpataru Vivant - North by Alder Residency Private Limited (Kalpataru) is a 647-unit BMC-sanctioned project in Jogeshwari East, Mumbai 400060, registered with MahaRERA in 6 phases, with possession dates from December 2028 to June 2029. 579 units booked out of total 647 units. The concrete structure (RCC) is complete.

Read full summary

Kalpataru Vivant - North is a BMC-sanctioned project by Alder Residency Private Limited in Jogeshwari East, Mumbai 400060, registered with MahaRERA as 6 phases (P51800045409, P51800047620, P51800047621, P51800051153, P51800051328, P51800077538). The first phase was launched in May 2022. Together the phases have 647 units in 6 buildings, with 2 and 3 BHK homes as registered with MahaRERA. On MahaRERA, 4 are completed and 2 are active.

The phases' registered possession dates run from December 2028 to June 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 25% complete. 5 of the 6 phases have their structure complete.

579 units booked out of total 647 units (89%). Since the July 2026 update, 17 more units have been booked.

Kalpataru's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA42
Total units across these projects6,678
Completed without extending the possession date19
Completed after an extension8
Lapsed0
Under construction15
Possession date extended on the builder's application9
Typical time from launch to 100% structure5 years 10 months
MahaRERA complaints (filed by or against the builder), all Kalpataru projects225 (21 of 42 projects)

See all Kalpataru projects →