Shree Krishna, Powai

by Shreem Properties · Powai, Mumbai 400087 · Map

Launched
May 2022First of 2 phases
Possession (MahaRERA)
Mar 2027 – Jun 2029Not extended
Concrete structure
73%Weighted across 2 phases
Booked
195 of 36054% · 166 in Jul 2026
Buildings
51.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
143
2 BHK
132
3 BHK
80
Other units
5
Total units
360
Buildings
5
Land
1.7 acres
Phases
2
MahaRERA complaints
0
Reserved units
48

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
SHREE KRISHNA WING A and B
Nearing possession
P51800045520160100%89%
SHREE KRISHNA Wing C,D and E
Mid-construction
PR118000250255419550%25%
Show updates by phase

SHREE KRISHNA WING A and B (P51800045520)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%25%147
100%100%1%118
100%100%0%93
100%35%0%67

"–" means MahaRERA shows no figure for that update.

SHREE KRISHNA Wing C,D and E (PR1180002502554)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%50%1%48
100%36%0%48

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)73%
Finishes, lifts and services12%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 65%Oct 2026: Concrete structure (RCC) 73%Jul 2026: Final finishes 0%Oct 2026: Final finishes 12%Excavation 100%Concrete structure (RCC) 73%Final finishes 12%

How to read construction stages

About this project

Shree Krishna by Shreem Properties is a 360-unit BMC-sanctioned project in Powai, Mumbai 400087, registered with MahaRERA in 2 phases, with possession dates from March 2027 to June 2029. 195 units booked out of total 360 units. The concrete structure (RCC) is 73% complete.

Read full summary

Shree Krishna is a BMC-sanctioned project by Shreem Properties in Powai, Mumbai 400087, registered with MahaRERA as 2 phases (P51800045520, PR1180002502554). The first phase was launched in May 2022. Together the phases have 360 units in 5 buildings: 355 homes (1, 2 and 3 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA.

The phases' registered possession dates run from March 2027 to June 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 73% complete and final finishes 12% complete. Neither phase has its structure complete.

195 units booked out of total 360 units (54%). Since the July 2026 update, 29 more units have been booked.