Serene Shelter, Kurla East
by Nishat Ataullah Ansari · Kurla East, Mumbai 400024 · Map
- Launched
- May 20223 yrs 7 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 1 yr 4 mths
- Concrete structure
- 0%Early stage
- Booked
- 11 of 4127%
- Buildings
- 11.3 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 14
- 2 BHK
- 24
- Other units
- 3
- Total units
- 41
- Buildings
- 1
- Land
- 1.3 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Work not started as of Oct 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 11 | |
| 0% | 0% | 0% | 11 | |
| 0% | 0% | 0% | 11 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Serene Shelter by Nishat Ataullah Ansari is a 41-unit SRA-sanctioned project in Kurla East, Mumbai 400024, launched in May 2022 with possession due in April 2027. 11 units booked out of total 41 units. Work on the concrete structure (RCC) has not started.
Read full summary
Serene Shelter is an SRA-sanctioned project by Nishat Ataullah Ansari in Kurla East, Mumbai 400024, registered with MahaRERA as P51800045597. It was launched in May 2022. It has 41 units in 1 building: 38 homes (1 and 2 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2027, extended by 1 year 4 months from the original December 2025. Construction: excavation not started, structure (RCC) not started, final finishes not started.
11 units booked out of total 41 units (27%).