Sadguru Avenue, Dahisar
by Sadguru Krupa Developers · Dahisar, Mumbai 400068 · Map
- Launched
- Jun 20223 yrs 6 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 1 yr
- Concrete structure
- 98%Mid-construction
- Booked
- 92 of 13270%
- Buildings
- 30.7 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 46
- 2 BHK
- 80
- Other units
- 6
- Total units
- 132
- Buildings
- 3
- Land
- 0.7 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 98% | 92% | 92 | |
| 100% | 95% | 80% | 92 | |
| 100% | 77% | 0% | 88 | |
| 100% | 68% | 0% | 50 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400068
Projects with 60–300 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 6 mths | 4 yrs |
| Possession date extended | By 1 yr | 2 of 3 |
| Possession date (MahaRERA) | Dec 2026 | Dec 2026 |
| Concrete structure (RCC) | 98% | 100% |
| Units booked | 70% | 54% |
| MahaRERA complaints (filed by or against the builder) | 1 | 0 |
The 3 projects
- Shiv Parbat, Dahisar
- Ray, Dahisar
- Jeandveevishwanath, Dahisar
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shiv Parbat | June 2022 | March 2027 | 100% | 2 units booked out of total 85 units |
| Ray | October 2021 | April 2026 | 100% | 137 units booked out of 140 units for sale |
| Jeandveevishwanath | October 2021 | December 2026 | 0% | 106 units booked out of total 198 units |
About this project
Sadguru Avenue by Sadguru Krupa Developers is a 132-unit BMC-sanctioned project in Dahisar, Mumbai 400068, launched in June 2022 with possession due in December 2026. 92 units booked out of total 132 units. The concrete structure (RCC) is 98% complete.
Read full summary
Sadguru Avenue is a BMC-sanctioned project by Sadguru Krupa Developers in Dahisar, Mumbai 400068, registered with MahaRERA as P51800045763. It was launched in June 2022. It has 132 units in 3 buildings: 126 homes (1 and 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) 98% complete, final finishes 92% complete.
92 units booked out of total 132 units (70%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 95% to 98%.