- Launched
- Jun 20223 yrs 9 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 9 mths
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 113 of 16170% · 25 rehab units
- Buildings
- 10.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale113 booked out of 161 units
Rehab25 units for existing members
Total 186 units. Rehab units are not for sale.
Project facts
- Other units
- 186
- Total units
- 186
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 161
- Rehab units
- 25
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 113 | |
| 100% | 100% | 45% | 90 | |
| 100% | 25% | 0% | – | |
| 100% | 25% | 0% | 37 |
"–" means MahaRERA shows no figure for that update.
About this project
Avani Signature by Avani Buildcon is a 186-unit BMC-sanctioned project in Ghatkopar West, Mumbai 400086, launched in June 2022 with possession due in December 2026. 113 units booked out of 161 units for sale. The concrete structure (RCC) is complete.
Read full summary
Avani Signature is a BMC-sanctioned project by Avani Buildcon in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800045772. It was launched in June 2022. It has 186 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 186 units, 161 are for sale and 25 are rehab units for existing members.
Its registered possession date is December 2026, extended by 9 months from the original March 2026. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
113 units booked out of 161 units for sale (70%). Since the July 2026 update, 23 more units have been booked.