Parmar Pearl - Jay Koteshwar Nagar Chs Ltd, Malad East
Ready to move
by Parmar Constructions Private Limited · Malad East, Mumbai 400097 · Map
- Launched
- Jun 20222 yrs 11 mths originally promised
- Possession (MahaRERA)
- Nov 2026Extended by 1 yr 6 mths
- Concrete structure
- 100%Ready to move
- Booked
- 27 of 3382% · 23 in Jul 2026
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 8
- 2 BHK
- 14
- Other units
- 11
- Total units
- 33
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 27 | |
| 100% | 100% | 95% | 23 | |
| 100% | 100% | 95% | 19 | |
| 100% | 90% | 0% | 13 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400097
Projects with 10–50 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 11 mths | 2 yrs 7 mths |
| Possession date extended | By 1 yr 6 mths | 2 of 3 |
| Possession date (MahaRERA) | Nov 2026 | Dec 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked | 82% | 90% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Tillibai Apartment Co-Op. Hsg. Soc. Ltd, Malad East
- Kanak Heights - Geeta Bhavan Chsl, Malad East
- Hill Star, Malad East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Tillibai Apartment Co-Op. Hsg. Soc. Ltd | September 2022 | December 2026 | 100% | 13 units booked out of total 20 units |
| Kanak Heights - Geeta Bhavan Chsl | November 2022 | November 2026 | 100% | 32 units booked out of 32 units for sale |
| Hill Star | January 2023 | June 2027 | 100% | 18 units booked out of total 20 units |
About this project
Parmar Pearl - Jay Koteshwar Nagar Chs Ltd by Parmar Constructions Private Limited is a 33-unit BMC-sanctioned project in Malad East, Mumbai 400097, launched in June 2022 with possession due in November 2026. 27 units booked out of total 33 units. The concrete structure (RCC) is complete.
Read full summary
Parmar Pearl - Jay Koteshwar Nagar Chs Ltd is a BMC-sanctioned project by Parmar Constructions Private Limited in Malad East, Mumbai 400097, registered with MahaRERA as P51800045853. It was launched in June 2022. It has 33 units in 1 building: 22 homes (1 and 2 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is November 2026, extended by 1 year 6 months from the original May 2025. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
27 units booked out of total 33 units (82%). Since the July 2026 update, 4 more units have been booked and the possession date has moved from May 2026 to November 2026.