Asmi Business Centre, Goregaon East

by Asmi Corporation · Goregaon East, Mumbai 400063 · Map

Launched
Jun 20223 yrs 6 mths originally promised
Possession (MahaRERA)
Dec 2028Extended by 3 yrs
Concrete structure
0%Early stage
Booked (free sale)
97 of 16260%
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale97 booked out of 162 units

Land-owner share2 units, not for sale

Total 164 units. Land-owner units are not for sale.

Project facts

Other units
164
Total units
164
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
162
Land-owner share (not for sale)
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%97
100%0%0%88
100%0%0%78
100%0%0%75

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Asmi Business Centre by Asmi Corporation is a 164-unit BMC-sanctioned project in Goregaon East, Mumbai 400063, launched in June 2022 with possession due in December 2028. 97 units booked out of 162 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Asmi Business Centre is a BMC-sanctioned project by Asmi Corporation in Goregaon East, Mumbai 400063, registered with MahaRERA as P51800046269. It was launched in June 2022. It has 164 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 164 units, 162 are for sale and 2 are the land-owner's share, not for sale.

Its registered possession date is December 2028, extended by 3 years from the original December 2025. Construction: excavation complete, structure (RCC) not started, final finishes not started.

97 units booked out of 162 units for sale (60%). Since the July 2026 update, 9 more units have been booked.