Khernagar Shriram, Bandra East

by Khernagar Shriram Chs Ltd · Bandra East, Mumbai 400051 · Map

Launched
Jun 20223 yrs 10 mths originally promised
Possession (MahaRERA)
Apr 2027Extended by 1 yr
Concrete structure
80%Mid-construction
Booked
12 of 2843%
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
1
1 BHK
3
2 BHK
12
3 BHK
3
Other units
9
Total units
28
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)80%
Finishes, lifts and services10%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 80%Oct 2026: Concrete structure (RCC) 80%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 10%Oct 2026: Final finishes 10%Excavation 100%Concrete structure (RCC) 80%Final finishes 10%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%80%10%12
100%80%10%12
100%0%0%14
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Khernagar Shriram by Khernagar Shriram Chs Ltd is a 28-unit MHADA-sanctioned project in Bandra East, Mumbai 400051, launched in June 2022 with possession due in April 2027. 12 units booked out of total 28 units. The concrete structure (RCC) is 80% complete.

Read full summary

Khernagar Shriram is a MHADA-sanctioned project by Khernagar Shriram Chs Ltd in Bandra East, Mumbai 400051, registered with MahaRERA as P51800046396. It was launched in June 2022. It has 28 units in 1 building: 19 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2027, extended by 1 year from the original April 2026. Construction: excavation complete, structure (RCC) 80% complete, final finishes 10% complete.

12 units booked out of total 28 units (43%).