Ashok Aura - RJ Commercial, Andheri East
by Sanyam Realtors Private Limited · Andheri East, Mumbai 400099 · Map
- Launched
- Aug 20223 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 2 yrs
- Concrete structure
- 100%Nearing possession
- Booked
- 0 of 110%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 11
- Total units
- 11
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 0 | |
| 100% | 100% | 0% | 0 | |
| 100% | 60% | 0% | 0 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Ashok Aura - RJ Commercial by Sanyam Realtors Private Limited is an 11-unit BMC-sanctioned project in Andheri East, Mumbai 400099, launched in August 2022 with possession due in December 2027. 0 units booked out of total 11 units. The concrete structure (RCC) is complete.
Read full summary
Ashok Aura - RJ Commercial is a BMC-sanctioned project by Sanyam Realtors Private Limited in Andheri East, Mumbai 400099, registered with MahaRERA as P51800046477. It was launched in August 2022. It has 11 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, extended by 2 years from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes not started.
0 units booked out of total 11 units (0%).