Zee Manu Bharati, Andheri West

Ready to move

by Zee Rpm Properties LLP · Andheri West, Mumbai 400058 · Map

Launched
Aug 20224 yrs 7 mths promised
Possession (MahaRERA)
Mar 2027Not extended
Concrete structure
100%Ready to move
Booked
23 of 3566%
Buildings
30.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
3
3 BHK
12
Other units
20
Total units
35
Buildings
3
Land
0.5 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 90%Dec 2025: Excavation 99%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 98%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 90%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%23
100%100%100%–
99%100%90%–
90%98%0%23

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Zee Manu Bharati by Zee Rpm Properties LLP is a 35-unit BMC-sanctioned project in Andheri West, Mumbai 400058, launched in August 2022 with possession due in March 2027. 23 units booked out of total 35 units. The concrete structure (RCC) is complete.

Read full summary

Zee Manu Bharati is a BMC-sanctioned project by Zee Rpm Properties LLP in Andheri West, Mumbai 400058, registered with MahaRERA as P51800046578. It was launched in August 2022. It has 35 units in 3 buildings: 15 homes (2 and 3 BHK) and 20 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

23 units booked out of total 35 units (66%).