Atmiya Centria, Santacruz East
by Upturn Properties LLP · Santacruz East, Mumbai 400055 · Map
- Launched
- Aug 20224 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 50%Mid-construction
- Booked (free sale)
- 174 of 20087% · 60 rehab units
- Buildings
- 20.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale174 booked out of 200 units
Rehab60 units for existing members
Total 260 units. Rehab units are not for sale.
Project facts
- 1 RK
- 10
- 1 BHK
- 159
- 2 BHK
- 82
- Other units
- 9
- Total units
- 260
- Buildings
- 2
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 200
- Rehab units
- 60
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 50% | 50% | 50% | 174 | |
| 100% | 100% | 100% | 133 | |
| 100% | 95% | 25% | 133 | |
| 100% | 83% | 25% | 48 |
"–" means MahaRERA shows no figure for that update.
About this project
Atmiya Centria by Upturn Properties LLP is a 260-unit MHADA-sanctioned project in Santacruz East, Mumbai 400055, launched in August 2022 with possession due in December 2026. 174 units booked out of 200 units for sale. The concrete structure (RCC) is 50% complete.
Read full summary
Atmiya Centria is a MHADA-sanctioned project by Upturn Properties LLP in Santacruz East, Mumbai 400055, registered with MahaRERA as P51800046598. It was launched in August 2022. It has 260 units in 2 buildings: 251 homes (1 RK, 1 BHK and 2 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 260 units, 200 are for sale and 60 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation 50% complete, structure (RCC) 50% complete, final finishes 50% complete.
174 units booked out of 200 units for sale (87%). Since the July 2026 update, 41 more units have been booked and the reported concrete structure (RCC) has gone from 100% to 50%.