- Launched
- Sep 20223 yrs 3 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 1 yr
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 178 of 22181% · 182 rehab units
- Buildings
- 50.7 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale178 booked out of 221 units
Rehab182 units for existing members
Total 403 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 322
- 2 BHK
- 69
- Other units
- 12
- Total units
- 403
- Buildings
- 5
- Land
- 0.7 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 221
- Rehab units
- 182
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 178 | |
| 100% | 100% | 0% | 163 | |
| 100% | 78% | 0% | 150 | |
| 100% | 78% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Inspire Residency by Sardar Realty is a 403-unit SRA-sanctioned project in Andheri East, Mumbai 400093, launched in September 2022 with possession due in December 2026. 178 units booked out of 221 units for sale. The concrete structure (RCC) is complete.
Read full summary
Inspire Residency is an SRA-sanctioned project by Sardar Realty in Andheri East, Mumbai 400093, registered with MahaRERA as P51800046897. It was launched in September 2022. It has 403 units in 5 buildings: 391 homes (1 and 2 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 403 units, 221 are for sale and 182 are rehab units for existing members.
Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
178 units booked out of 221 units for sale (81%). Since the July 2026 update, 15 more units have been booked.