Metro Crown, Vikhroli

by Metro Enterprises · Vikhroli, Mumbai 400079 · Map

Launched
Sep 20225 yrs 3 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
70%Mid-construction
Booked
–
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
42
2 BHK
31
Total units
73
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)70%
Finishes, lifts and services10%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 70%Dec 2025: Concrete structure (RCC) 70%Jul 2026: Concrete structure (RCC) 70%Dec 2024: Final finishes 10%Dec 2025: Final finishes 10%Jul 2026: Final finishes 10%Excavation 100%Concrete structure (RCC) 70%Final finishes 10%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%70%10%–
100%70%10%–
100%70%10%11

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Metro Crown by Metro Enterprises is a 73-unit project in Vikhroli, Mumbai 400079, launched in September 2022 with possession due in December 2027. The concrete structure (RCC) is 70% complete.

Read full summary

Metro Crown is a project by Metro Enterprises in Vikhroli, Mumbai 400079, registered with MahaRERA as P51800047023. It was launched in September 2022. It has 73 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 70% complete, final finishes 10% complete.