Skip to main content

Pahuja Business Avenue Phase-I, Chandivali

by Shakti Constructions · Chandivali, Mumbai 400072 · Map

Launched
Oct 20224 yrs 2 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
10%Mid-construction
Booked (free sale)
34 of 10134% · 7 rehab units
Buildings
10.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale34 booked out of 101 units

Rehab7 units for existing members

Total 108 units. Rehab units are not for sale.

Project facts

Other units
108
Total units
108
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
1
Free-sale units
101
Rehab units
7

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)10%
Finishes, lifts and services70%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 10%Dec 2025: Concrete structure (RCC) 85%Jul 2026: Concrete structure (RCC) 10%Oct 2026: Concrete structure (RCC) 10%Dec 2024: Final finishes 10%Dec 2025: Final finishes 10%Jul 2026: Final finishes 70%Oct 2026: Final finishes 70%Excavation 100%Final finishes 70%Concrete structure (RCC) 10%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%10%70%34
100%10%70%34
100%85%10%22
100%10%10%11

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Pahuja Business Avenue Phase-I by Shakti Constructions is a 108-unit BMC-sanctioned project in Chandivali, Mumbai 400072, launched in October 2022 with possession due in December 2026. 34 units booked out of 101 units for sale. The concrete structure (RCC) is 10% complete.

Read full summary

Pahuja Business Avenue Phase-I is a BMC-sanctioned project by Shakti Constructions in Chandivali, Mumbai 400072, registered with MahaRERA as P51800047394. It was launched in October 2022. It has 108 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 108 units, 101 are for sale and 7 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 10% complete, final finishes 70% complete.

34 units booked out of 101 units for sale (34%).