Linkbay Residences Phase I, Andheri West

by Portsmouth Buildcon Private Limited · Andheri West, Mumbai 400053 · Map

Launched
Nov 20225 yrs 11 mths promised
Possession (MahaRERA)
Oct 2028Not extended
Concrete structure
90%Mid-construction
Booked
451 of 58977%
Buildings
62.5 acres
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
1
2 BHK
95
3 BHK
401
4 BHK
64
Other units
28
Total units
589
Buildings
6
Land
2.5 acres
Phases
1
MahaRERA complaints
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)90%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 98%Dec 2025: Excavation 98%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 83%Oct 2026: Concrete structure (RCC) 90%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 90%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%0%451
100%83%0%451
98%0%0%417
98%0%0%372

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Linkbay Residences Phase I by Portsmouth Buildcon Private Limited is a 589-unit BMC-sanctioned project in Andheri West, Mumbai 400053, launched in November 2022 with possession due in October 2028. 451 units booked out of total 589 units. The concrete structure (RCC) is 90% complete.

Read full summary

Linkbay Residences Phase I is a BMC-sanctioned project by Portsmouth Buildcon Private Limited in Andheri West, Mumbai 400053, registered with MahaRERA as P51800047539. It was launched in November 2022. It has 589 units in 6 buildings: 561 homes (1, 2, 3 and 4 BHK) and 28 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is October 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 90% complete, final finishes not started.

451 units booked out of total 589 units (77%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 83% to 90%.