Roswalt Zaiden, Jogeshwari West
by A S Hightech LLP · Jogeshwari West, Mumbai 400102 · Map
- Launched
- Nov 20226 yrs 1 mth promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 39%Mid-construction
- Booked
- 1,227 of 1,51881% · 949 in Jul 2026
- Buildings
- 55.4 acres
- MahaRERA complaints
- 21Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 777
- 2 BHK
- 586
- 3 BHK
- 11
- 4 BHK
- 50
- Other units
- 94
- Total units
- 1,518
- Buildings
- 5
- Land
- 5.4 acres
- Phases
- 1
- MahaRERA complaints
- 21
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 80% | 39% | 0% | 1,227 | |
| 80% | 28% | 0% | 949 | |
| 75% | 27% | 0% | 949 | |
| 25% | 30% | 0% | 604 |
"–" means MahaRERA shows no figure for that update.
About this project
Roswalt Zaiden by A S Hightech LLP is a 1,518-unit SRA-sanctioned project in Jogeshwari West, Mumbai 400102, launched in November 2022 with possession due in December 2028. 1,227 units booked out of total 1,518 units. The concrete structure (RCC) is 39% complete.
Read full summary
Roswalt Zaiden is an SRA-sanctioned project by A S Hightech LLP in Jogeshwari West, Mumbai 400102, registered with MahaRERA as P51800047680. It was launched in November 2022. It has 1,518 units in 5 buildings: 1,424 homes (1, 2, 3 and 4 BHK) and 94 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation 80% complete, structure (RCC) 39% complete, final finishes not started.
1,227 units booked out of total 1,518 units (81%). Since the July 2026 update, 278 more units have been booked and the reported concrete structure (RCC) has gone from 28% to 39%.