Orchid Tower, Borivali West
Ready to move
by Shree Laxmi Estate Pvt Ltd · Borivali West, Mumbai 400092 · Map
- Launched
- Nov 20223 yrs 4 mths originally promised
- Possession (MahaRERA)
- Mar 2027Extended by 1 yr
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 106 of 18757%
- Buildings
- 10.5 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale106 booked out of 187 units
Land-owner share7 units, not for sale
Total 194 units. Land-owner units are not for sale.
Project facts
- Other units
- 194
- Total units
- 194
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 187
- Land-owner share (not for sale)
- 7
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 106 | |
| 100% | 100% | 50% | 101 | |
| 100% | 95% | 0% | 83 | |
| 100% | 80% | 0% | 62 |
"–" means MahaRERA shows no figure for that update.
About this project
Orchid Tower by Shree Laxmi Estate Pvt Ltd is a 194-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in November 2022 with possession due in March 2027. 106 units booked out of 187 units for sale. The concrete structure (RCC) is complete.
Read full summary
Orchid Tower is a BMC-sanctioned project by Shree Laxmi Estate Pvt Ltd in Borivali West, Mumbai 400092, registered with MahaRERA as P51800047733. It was launched in November 2022. It has 194 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 194 units, 187 are for sale and 7 are the land-owner's share, not for sale.
Its registered possession date is March 2027, extended by 1 year from the original March 2026. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
106 units booked out of 187 units for sale (57%). Since the July 2026 update, 5 more units have been booked.