Mars, Powai
by Suncity Housing · Powai, Mumbai 400076 · Map
- Launched
- Nov 2022First of 2 phases
- Possession (MahaRERA)
- Dec 2027 – Mar 2030Not extended
- Concrete structure
- 64%Weighted across 2 phases
- Booked
- 291 of 43966% · 165 in Jul 2026
- Buildings
- 20.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 279
- 2 BHK
- 160
- Total units
- 439
- Buildings
- 2
- Land
- 0.2 acres
- Phases
- 2
- MahaRERA complaints
- 0
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Mars - Wing - B Nearing possession | P51800047829 | 233 | 100% | 81% | |
| Mars Wing-C Mid-construction | P51800080587 | 206 | 24% | 50% |
Show updates by phase
Mars - Wing - B (P51800047829)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 73% | 189 | |
| 100% | 100% | 0% | 165 | |
| 100% | 100% | 0% | 165 | |
| 80% | 0% | 0% | 68 |
"–" means MahaRERA shows no figure for that update.
Mars Wing-C (P51800080587)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 24% | 0% | 102 | |
| 100% | 3% | 0% | 0 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Mars by Suncity Housing is a 439-unit BMC-sanctioned project in Powai, Mumbai 400076, registered with MahaRERA in 2 phases, with possession dates from December 2027 to March 2030. 291 units booked out of total 439 units. The concrete structure (RCC) is 64% complete.
Read full summary
Mars is a BMC-sanctioned project by Suncity Housing in Powai, Mumbai 400076, registered with MahaRERA as 2 phases (P51800047829, P51800080587). The first phase was launched in November 2022. Together the phases have 439 units in 2 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Both phases are active on MahaRERA.
The phases' registered possession dates run from December 2027 to March 2030; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 64% complete and final finishes 39% complete. Neither phase has its structure complete.
291 units booked out of total 439 units (66%). Since the July 2026 update, 126 more units have been booked.