Turner House, Bandra West

by Variegate Real Estate Private Limited · Bandra West, Mumbai 400050 · Map

Launched
Dec 20225 yrs 3 mths promised
Possession (MahaRERA)
Mar 2028Not extended
Concrete structure
75%Mid-construction
Booked
9 of 6514%
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
65
Total units
65
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)75%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 75%Dec 2025: Concrete structure (RCC) 75%Jul 2026: Concrete structure (RCC) 75%Oct 2026: Concrete structure (RCC) 75%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 75%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%75%0%9
100%75%0%–
100%75%0%–
100%75%0%9

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Turner House by Variegate Real Estate Private Limited is a 65-unit BMC-sanctioned project in Bandra West, Mumbai 400050, launched in December 2022 with possession due in March 2028. 9 units booked out of total 65 units. The concrete structure (RCC) is 75% complete.

Read full summary

Turner House is a BMC-sanctioned project by Variegate Real Estate Private Limited in Bandra West, Mumbai 400050, registered with MahaRERA as P51800047873. It was launched in December 2022. It has 65 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 75% complete, final finishes not started.

9 units booked out of total 65 units (14%).