Signet, Borivali West

by Dg Builders · Borivali West, Mumbai 400092 · Map

Launched
Dec 20223 yrs 10 mths promised
Possession (MahaRERA)
Oct 2026Not extended
Concrete structure
90%Mid-construction
Booked (free sale)
41 of 5279% · 1 rehab units
Buildings
10.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale41 booked out of 52 units

Rehab1 unit for existing members

Total 53 units. Rehab units are not for sale.

Project facts

Other units
53
Total units
53
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
1
Free-sale units
52
Rehab units
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)90%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 90%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 90%Oct 2026: Concrete structure (RCC) 90%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 90%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%0%41
100%90%0%–
100%90%0%–
100%90%0%22

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Signet by Dg Builders is a 53-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in December 2022 with possession due in October 2026. 41 units booked out of 52 units for sale. The concrete structure (RCC) is 90% complete.

Read full summary

Signet is a BMC-sanctioned project by Dg Builders in Borivali West, Mumbai 400092, registered with MahaRERA as P51800047941. It was launched in December 2022. It has 53 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 53 units, 52 are for sale and 1 is a rehab unit for existing members.

Its registered possession date is October 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 90% complete, final finishes not started.

41 units booked out of 52 units for sale (79%).