Skip to main content

Durga Gayatri, Vile Parle West

by Manoj Mohanlal Goradia · Vile Parle West, Mumbai 400056 · Map

Launched
Dec 20222 yrs 11 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 1 yr 1 mth
Concrete structure
100%Nearing possession
Booked (free sale)
15 of 1883% · 17 rehab units
Buildings
10.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale15 booked out of 18 units

Rehab17 units for existing members

Total 35 units. Rehab units are not for sale.

Project facts

2 BHK
12
3 BHK
23
Total units
35
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
0
Free-sale units
18
Rehab units
17

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 40%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%15
100%100%0%15
100%40%0%11
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Durga Gayatri by Manoj Mohanlal Goradia is a 35-unit BMC-sanctioned project in Vile Parle West, Mumbai 400056, launched in December 2022 with possession due in December 2026. 15 units booked out of 18 units for sale. The concrete structure (RCC) is complete.

Read full summary

Durga Gayatri is a BMC-sanctioned project by Manoj Mohanlal Goradia in Vile Parle West, Mumbai 400056, registered with MahaRERA as P51800048238. It was launched in December 2022. It has 35 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 35 units, 18 are for sale and 17 are rehab units for existing members.

Its registered possession date is December 2026, extended by 1 year 1 month from the original November 2025. Construction: excavation complete, structure (RCC) complete, final finishes not started.

15 units booked out of 18 units for sale (83%).