- Launched
- Jan 20233 yrs 9 mths promised
- Possession (MahaRERA)
- Oct 2026Not extended
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 42 of 5084%
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale42 booked out of 50 units
Land-owner share22 units, not for sale
Total 72 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 34
- 2 BHK
- 34
- Other units
- 4
- Total units
- 72
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 50
- Land-owner share (not for sale)
- 22
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 42 | |
| 100% | 95% | 50% | 42 | |
| 100% | 96% | 10% | 32 | |
| 100% | 80% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400083
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 9 mths | 3 yrs 10 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | Oct 2026 | Dec 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 84% | 95% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Swastik Tulip, Vikhroli
- Gs Casa, Vikhroli
- Vrindavan Elite, Vikhroli
- Kannamwar Nagar Datta Niwas, Vikhroli
- Swastik Coral, Vikhroli
- Puneet Amarjyoti, Vikhroli
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Swastik Tulip | January 2023 | December 2026 | 100% | 118 units booked out of total 120 units |
| Gs Casa | February 2023 | December 2026 | 81% | 45 units booked out of total 68 units |
| Vrindavan Elite | December 2022 | October 2026 | 100% | 91 units booked out of 92 units for sale |
| Kannamwar Nagar Datta Niwas | February 2023 | December 2026 | 100% | 91 units booked out of 100 units for sale |
| Swastik Coral | March 2023 | December 2027 | 100% | 75 units booked out of total 121 units |
| Puneet Amarjyoti | September 2022 | December 2026 | 83% | 54 units booked out of total 54 units |
About this project
Meadows 83 by Shreeji Realtors is a 72-unit BMC-sanctioned project in Vikhroli, Mumbai 400083, launched in January 2023 with possession due in October 2026. 42 units booked out of 50 units for sale. The concrete structure (RCC) is complete.
Read full summary
Meadows 83 is a BMC-sanctioned project by Shreeji Realtors in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800048486. It was launched in January 2023. It has 72 units in 1 building: 68 homes (1 and 2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 72 units, 50 are for sale and 22 are the land-owner's share, not for sale.
Its registered possession date is October 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
42 units booked out of 50 units for sale (84%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 95% to 100%.