Elite Residency, Kurla West

by Elite Construction Co · Kurla West, Mumbai 400070 · Map

Launched
Jan 20232 yrs 11 mths originally promised
Possession (MahaRERA)
Jun 2027Extended by 1 yr 6 mths
Concrete structure
80%Mid-construction
Booked (free sale)
3 of 933% · 5 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale3 booked out of 9 units

Rehab5 units for existing members

Total 14 units. Rehab units are not for sale.

Project facts

1 RK
1
1 BHK
4
2 BHK
6
3 BHK
3
Total units
14
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
9
Rehab units
5

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)80%
Finishes, lifts and services10%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 60%Jul 2026: Concrete structure (RCC) 75%Oct 2026: Concrete structure (RCC) 80%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 10%Oct 2026: Final finishes 10%Excavation 100%Concrete structure (RCC) 80%Final finishes 10%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%80%10%3
100%75%10%3
100%60%0%3
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400070

Projects with up to 30 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400070
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 11 mths2 yrs 5 mths
Possession date extendedBy 1 yr 6 mths2 of 3
Possession date (MahaRERA)Jun 2027Dec 2026
Concrete structure (RCC)80%90%
Units booked (free sale)33%29%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Elite Residency by Elite Construction Co is a 14-unit BMC-sanctioned project in Kurla West, Mumbai 400070, launched in January 2023 with possession due in June 2027. 3 units booked out of 9 units for sale. The concrete structure (RCC) is 80% complete.

Read full summary

Elite Residency is a BMC-sanctioned project by Elite Construction Co in Kurla West, Mumbai 400070, registered with MahaRERA as P51800048557. It was launched in January 2023. It has 14 units in 1 building, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 14 units, 9 are for sale and 5 are rehab units for existing members.

Its registered possession date is June 2027, extended by 1 year 6 months from the original December 2025. Construction: excavation complete, structure (RCC) 80% complete, final finishes 10% complete.

3 units booked out of 9 units for sale (33%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 75% to 80%.