Krishna Bhuvan, Vile Parle East

by Ashraj Developers Private Limited · Vile Parle East, Mumbai 400057 · Map

Launched
Jan 20234 yrs 5 mths promised
Possession (MahaRERA)
Jun 2027Not extended
Concrete structure
100%Nearing possession
Booked
–
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
2
2 BHK
3
3 BHK
2
Other units
13
Total units
20
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 2%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 80%Jul 2026: Final finishes 80%Oct 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 100%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%80%–
100%100%80%–
100%100%80%–
100%2%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Krishna Bhuvan by Ashraj Developers Private Limited is a 20-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in January 2023 with possession due in June 2027. The concrete structure (RCC) is complete.

Read full summary

Krishna Bhuvan is a BMC-sanctioned project by Ashraj Developers Private Limited in Vile Parle East, Mumbai 400057, registered with MahaRERA as P51800048612. It was launched in January 2023. It has 20 units in 1 building: 7 homes (1, 2 and 3 BHK) and 13 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.