Skip to main content

Sheetal Shree Kailash, Santacruz East

by Toughcons Realtors Private Limited · Santacruz East, Mumbai 400055 · Map

Launched
Jan 20231 yr 3 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 2 yrs 8 mths
Concrete structure
72%Mid-construction
Booked
25 of 2696%
Buildings
20.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
26
Total units
26
Buildings
2
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)72%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 63%Dec 2025: Concrete structure (RCC) 72%Jul 2026: Concrete structure (RCC) 72%Oct 2026: Concrete structure (RCC) 72%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 72%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%72%0%25
100%72%0%–
100%72%0%–
100%63%0%25

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sheetal Shree Kailash by Toughcons Realtors Private Limited is a 26-unit BMC-sanctioned project in Santacruz East, Mumbai 400055, launched in January 2023 with possession due in December 2026. 25 units booked out of total 26 units. The concrete structure (RCC) is 72% complete.

Read full summary

Sheetal Shree Kailash is a BMC-sanctioned project by Toughcons Realtors Private Limited in Santacruz East, Mumbai 400055, registered with MahaRERA as P51800048719. It was launched in January 2023. It has 26 units in 2 buildings, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 2 years 8 months from the original April 2024. Construction: excavation complete, structure (RCC) 72% complete, final finishes not started.

25 units booked out of total 26 units (96%).