Chouhan Landmark, Andheri West
by Chouhan Builders India HSG Development Pvt Ltd · Andheri West, Mumbai 400058 · Map
- Launched
- Jan 20232 yrs 11 mths originally promised
- Possession (MahaRERA)
- Nov 2027Extended by 1 yr 11 mths
- Concrete structure
- 95%Mid-construction
- Booked
- 4 of 3412% · 3 in Jul 2026
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 24
- 2 BHK
- 10
- Total units
- 34
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 95% | 0% | 4 | |
| 100% | 90% | 0% | 3 | |
| 100% | 74% | 0% | 3 | |
| 100% | 68% | 0% | 2 |
"–" means MahaRERA shows no figure for that update.
About this project
Chouhan Landmark by Chouhan Builders India HSG Development Pvt Ltd is a 34-unit BMC-sanctioned project in Andheri West, Mumbai 400058, launched in January 2023 with possession due in November 2027. 4 units booked out of total 34 units. The concrete structure (RCC) is 95% complete.
Read full summary
Chouhan Landmark is a BMC-sanctioned project by Chouhan Builders India HSG Development Pvt Ltd in Andheri West, Mumbai 400058, registered with MahaRERA as P51800048925. It was launched in January 2023. It has 34 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is November 2027, extended by 1 year 11 months from the original December 2025. Construction: excavation complete, structure (RCC) 95% complete, final finishes not started.
4 units booked out of total 34 units (12%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 90% to 95%.