Alora, Santacruz East
Ready to move
by Kolte-Patil Developers Limited · Santacruz East, Mumbai 400098 · Map
- Launched
- Jan 20234 yrs 4 mths promised
- Possession (MahaRERA)
- May 2027Not extended
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 63 of 9765% · 113 rehab units
- Buildings
- 51.3 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale63 booked out of 97 units
Rehab113 units for existing members
Total 210 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 20
- 2 BHK
- 146
- 3 BHK
- 42
- 4 BHK
- 2
- Total units
- 210
- Buildings
- 5
- Land
- 1.3 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 97
- Rehab units
- 113
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 63 | |
| 100% | 100% | 48% | 63 | |
| 100% | 84% | 0% | 63 | |
| 100% | 64% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Alora by Kolte-Patil Developers Limited is a 210-unit BMC-sanctioned project in Santacruz East, Mumbai 400098, launched in January 2023 with possession due in May 2027. 63 units booked out of 97 units for sale. The concrete structure (RCC) is complete.
Read full summary
Alora is a BMC-sanctioned project by Kolte-Patil Developers Limited in Santacruz East, Mumbai 400098, registered with MahaRERA as P51800049048. It was launched in January 2023. It has 210 units in 5 buildings, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 210 units, 97 are for sale and 113 are rehab units for existing members.
Its registered possession date is May 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
63 units booked out of 97 units for sale (65%).