Skip to main content

Elegant Residency, Andheri East

by Elegant Builders And Developers · Andheri East, Mumbai 400069 · Map

Launched
Feb 20233 yrs 10 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Nearing possession
Booked
62 of 6595% · 52 in Jul 2026
Buildings
10.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
65
Total units
65
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 80%Dec 2025: Concrete structure (RCC) 70%Jul 2026: Concrete structure (RCC) 80%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 10%Jul 2026: Final finishes 20%Oct 2026: Final finishes 60%Excavation 100%Concrete structure (RCC) 100%Final finishes 60%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%60%62
100%80%20%52
100%70%10%43
100%80%0%25

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Elegant Residency by Elegant Builders And Developers is a 65-unit SRA-sanctioned project in Andheri East, Mumbai 400069, launched in February 2023 with possession due in December 2026. 62 units booked out of total 65 units. The concrete structure (RCC) is complete.

Read full summary

Elegant Residency is an SRA-sanctioned project by Elegant Builders And Developers in Andheri East, Mumbai 400069, registered with MahaRERA as P51800049271. It was launched in February 2023. It has 65 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete.

62 units booked out of total 65 units (95%). Since the July 2026 update, 10 more units have been booked and the reported concrete structure (RCC) has gone from 80% to 100%.