Sarvodaya Heights, Ghatkopar West

by Cmg Enterprises · Ghatkopar West, Mumbai 400086 · Map

Launched
Feb 20232 yrs 7 mths originally promised
Possession (MahaRERA)
Sep 2026Extended by 1 yr
Concrete structure
100%Nearing possession
Booked (free sale)
20 of 5238% · 60 rehab units
Buildings
30.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale20 booked out of 52 units

Rehab60 units for existing members

Total 112 units. Rehab units are not for sale.

Project facts

2 BHK
55
3 BHK
56
4 BHK
1
Total units
112
Buildings
3
Land
0.7 acres
Phases
1
MahaRERA complaints
0
Free-sale units
52
Rehab units
60

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services53%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 82%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 20%Oct 2026: Final finishes 53%Excavation 100%Concrete structure (RCC) 100%Final finishes 53%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%53%20
100%100%20%14
100%90%0%13
100%82%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sarvodaya Heights by Cmg Enterprises is a 112-unit BMC-sanctioned project in Ghatkopar West, Mumbai 400086, launched in February 2023 with possession due in September 2026. 20 units booked out of 52 units for sale. The concrete structure (RCC) is complete.

Read full summary

Sarvodaya Heights is a BMC-sanctioned project by Cmg Enterprises in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800049428. It was launched in February 2023. It has 112 units in 3 buildings, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 112 units, 52 are for sale and 60 are rehab units for existing members.

Possession was due in September 2026, after an extension of 1 year from the original September 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 53% complete.

20 units booked out of 52 units for sale (38%). Since the July 2026 update, 6 more units have been booked.