Viceroy Prive, Kandivali East
by Simba Properties LLP · Kandivali East, Mumbai 400101 · Map
- Launched
- Feb 20234 yrs 10 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 100%Nearing possession
- Booked
- 60 of 6198% · 58 in Jul 2026
- Buildings
- 10.7 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 4 BHK
- 56
- Other units
- 5
- Total units
- 61
- Buildings
- 1
- Land
- 0.7 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 85% | 60 | |
| 100% | 100% | 10% | 58 | |
| 100% | 65% | 0% | 55 | |
| 100% | 24% | 0% | 51 |
"–" means MahaRERA shows no figure for that update.
About this project
Viceroy Prive by Simba Properties LLP is a 61-unit BMC-sanctioned project in Kandivali East, Mumbai 400101, launched in February 2023 with possession due in December 2027. 60 units booked out of total 61 units. The concrete structure (RCC) is complete.
Read full summary
Viceroy Prive is a BMC-sanctioned project by Simba Properties LLP in Kandivali East, Mumbai 400101, registered with MahaRERA as P51800049560. It was launched in February 2023. It has 61 units in 1 building: 56 homes (4 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 85% complete.
60 units booked out of total 61 units (98%). Since the July 2026 update, 2 more units have been booked.