Stellar Heights, Andheri East
by Starwing Developers Private Limited · Andheri East, Mumbai 400059 · Map
- Launched
- Feb 20233 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 6 mths
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 36 of 4090%
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale36 booked out of 40 units
Land-owner share14 units, not for sale
Total 54 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 9
- 2 BHK
- 43
- Other units
- 2
- Total units
- 54
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Reserved units
- 9
- Free-sale units
- 40
- Land-owner share (not for sale)
- 14
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 20% | 36 | |
| 100% | 100% | 20% | 9 | |
| 100% | 60% | 0% | 7 | |
| 100% | 45% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Stellar Heights by Starwing Developers Private Limited is a 54-unit BMC-sanctioned project in Andheri East, Mumbai 400059, launched in February 2023 with possession due in December 2026. 36 units booked out of 40 units for sale. The concrete structure (RCC) is complete.
Read full summary
Stellar Heights is a BMC-sanctioned project by Starwing Developers Private Limited in Andheri East, Mumbai 400059, registered with MahaRERA as P51800049642. It was launched in February 2023. It has 54 units in 1 building: 52 homes (1 and 2 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 54 units, 40 are for sale and 14 are the land-owner's share, not for sale.
Its registered possession date is December 2026, extended by 6 months from the original June 2026. Construction: excavation complete, structure (RCC) complete, final finishes 20% complete.
36 units booked out of 40 units for sale (90%). Since the July 2026 update, 27 more units have been booked.