Sheetal Lennie, Jogeshwari West
by D G Land Developers Private Limited · Jogeshwari West, Mumbai 400102 · Map
- Launched
- Feb 20233 yrs 10 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 80%Mid-construction
- Booked (free sale)
- 33 of 5659% · 29 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale33 booked out of 56 units
Rehab29 units for existing members
Total 85 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 29
- 2 BHK
- 9
- 3 BHK
- 28
- Other units
- 19
- Total units
- 85
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 56
- Rehab units
- 29
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 80% | 40% | 33 | |
| 100% | 80% | 40% | 33 | |
| 100% | 10% | 0% | 33 | |
| 100% | 10% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400102
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 10 mths | 3 yrs 11 mths |
| Possession date extended | No | 2 of 5 |
| Possession date (MahaRERA) | Dec 2026 | Dec 2026 |
| Concrete structure (RCC) | 80% | 100% |
| Units booked (free sale) | 59% | 40% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Woods Platina Wing C - Walnut Tower, Jogeshwari West
- Woods Platina Wing D - Oak Tower, Jogeshwari West
- Amaan Heights, Jogeshwari West
- Lashkaria Solitaire, Jogeshwari West
- Golden Jubilee, Jogeshwari West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Woods Platina Wing C - Walnut Tower | January 2023 | December 2026 | 100% | 35 units booked out of total 82 units |
| Woods Platina Wing D - Oak Tower | January 2023 | December 2026 | 100% | 44 units booked out of total 82 units |
| Amaan Heights | January 2023 | December 2028 | 100% | 38 units booked out of total 95 units |
| Lashkaria Solitaire | December 2022 | October 2027 | 40% | 16 units booked out of total 55 units |
| Golden Jubilee | December 2022 | December 2026 | 100% | 19 units booked out of total 61 units |
About this project
Sheetal Lennie by D G Land Developers Private Limited is an 85-unit BMC-sanctioned project in Jogeshwari West, Mumbai 400102, launched in February 2023 with possession due in December 2026. 33 units booked out of 56 units for sale. The concrete structure (RCC) is 80% complete.
Read full summary
Sheetal Lennie is a BMC-sanctioned project by D G Land Developers Private Limited in Jogeshwari West, Mumbai 400102, registered with MahaRERA as P51800049785. It was launched in February 2023. It has 85 units in 1 building: 66 homes (1, 2 and 3 BHK) and 19 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 85 units, 56 are for sale and 29 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 80% complete, final finishes 40% complete.
33 units booked out of 56 units for sale (59%).