Sunbeam Heights, Andheri West
by Sun Beam High Tech Developers Private Limited · Andheri West, Mumbai 400053 · Map
- Launched
- Mar 20234 yrs 9 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 75%Mid-construction
- Booked (free sale)
- 230 of 31673% · 6 rehab units
- Buildings
- 10.9 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale230 booked out of 316 units
Rehab6 units for existing members
Total 322 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 141
- 2 BHK
- 147
- 3 BHK
- 34
- Total units
- 322
- Buildings
- 1
- Land
- 0.9 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 316
- Rehab units
- 6
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 75% | 0% | 230 | |
| 100% | 75% | 0% | 216 | |
| 100% | 38% | 0% | 196 | |
| 100% | 0% | 0% | 131 |
"–" means MahaRERA shows no figure for that update.
About this project
Sunbeam Heights by Sun Beam High Tech Developers Private Limited is a 322-unit MHADA-sanctioned project in Andheri West, Mumbai 400053, launched in March 2023 with possession due in December 2027. 230 units booked out of 316 units for sale. The concrete structure (RCC) is 75% complete.
Read full summary
Sunbeam Heights is a MHADA-sanctioned project by Sun Beam High Tech Developers Private Limited in Andheri West, Mumbai 400053, registered with MahaRERA as P51800049875. It was launched in March 2023. It has 322 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 322 units, 316 are for sale and 6 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 75% complete, final finishes not started.
230 units booked out of 316 units for sale (73%). Since the July 2026 update, 14 more units have been booked.