Neelyog Regent, Ghatkopar West

by Ratan Builders · Ghatkopar West, Mumbai 400086 · Map

Launched
Mar 20235 yrs promised
Possession (MahaRERA)
Mar 2028Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
270 of 270100%
Buildings
10.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale270 booked out of 270 units

Land-owner share23 units, not for sale

Total 293 units. Land-owner units are not for sale.

Project facts

Other units
293
Total units
293
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
0
Free-sale units
270
Land-owner share (not for sale)
23

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services10%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 90%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 13%Jul 2026: Concrete structure (RCC) 92%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 10%Excavation 100%Concrete structure (RCC) 100%Final finishes 10%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%10%270
100%92%0%270
100%13%0%270
90%0%0%14

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Neelyog Regent by Ratan Builders is a 293-unit SRA-sanctioned project in Ghatkopar West, Mumbai 400086, launched in March 2023 with possession due in March 2028. 270 units booked out of 270 units for sale. The concrete structure (RCC) is complete.

Read full summary

Neelyog Regent is an SRA-sanctioned project by Ratan Builders in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800050133. It was launched in March 2023. It has 293 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 293 units, 270 are for sale and 23 are the land-owner's share, not for sale.

Its registered possession date is March 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 10% complete.

270 units booked out of 270 units for sale (100%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 92% to 100%.