Skip to main content

The Wave, Bandra West

by Webtech Realty LLP · Bandra West, Mumbai 400050 · Map

Launched
Mar 20233 yrs 4 mths promised
Possession (MahaRERA)
Jul 2026Not extended
Concrete structure
94%Mid-construction
Booked (free sale)
48 of 6574% · 20 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale48 booked out of 65 units

Rehab20 units for existing members

Total 85 units. Rehab units are not for sale.

Project facts

1 BHK
10
2 BHK
57
3 BHK
3
4 BHK
1
5+ BHK
6
Other units
8
Total units
85
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
65
Rehab units
20

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)94%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 94%Oct 2026: Concrete structure (RCC) 94%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 50%Oct 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 94%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%94%50%48
100%94%50%48
0%0%0%–
0%0%0%6

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400050

Projects with 30–200 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400050
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 4 mths2 yrs 1 mth
Possession date extendedNo1 of 3
Possession date (MahaRERA)Jul 2026Mar 2026
Concrete structure (RCC)94%70%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

The Wave by Webtech Realty LLP is an 85-unit BMC-sanctioned project in Bandra West, Mumbai 400050, launched in March 2023 with possession due in July 2026. 48 units booked out of 65 units for sale. The concrete structure (RCC) is 94% complete.

Read full summary

The Wave is a BMC-sanctioned project by Webtech Realty LLP in Bandra West, Mumbai 400050, registered with MahaRERA as P51800050188. It was launched in March 2023. It has 85 units in 1 building: 77 homes (1, 2, 3, 4 and 5+ BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 85 units, 65 are for sale and 20 are rehab units for existing members.

Possession was due in July 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 94% complete, final finishes 50% complete.

48 units booked out of 65 units for sale (74%).