by M/S Nexzone Fiscal Services Pvt Ltd · Bhandup West, Mumbai 400078 · Map

Launched
Mar 2023First of 2 phases
Possession (MahaRERA)
Dec 2027 – Dec 2029Not extended
Concrete structure
6%Weighted across 2 phases
Booked
306 of 38280% · 203 in Jul 2026
Buildings
20.1 acres
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
40
1 BHK
276
2 BHK
44
Other units
22
Total units
382
Buildings
2
Land
0.1 acres
Phases
2
MahaRERA complaints
3

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Marathon Neovalley Narmada Wing B
Mid-construction
P5180005026421610%94%
Marathon Neovalley Narmada Wing C
Early stage
P518000811121440%61%
Show updates by phase

Marathon Neovalley Narmada Wing B (P51800050264)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%10%0%204
100%0%0%203
100%0%0%199
80%0%0%193

"–" means MahaRERA shows no figure for that update.

Marathon Neovalley Narmada Wing C (P51800081112)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%102
0%0%0%0

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)6%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 60%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 6%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 6%Final finishes 0%

How to read construction stages

About this project

Marathon Neovalley Narmada by M/S Nexzone Fiscal Services Pvt Ltd is a 382-unit BMC-sanctioned project in Bhandup West, Mumbai 400078, registered with MahaRERA in 2 phases, with possession dates from December 2027 to December 2029. 306 units booked out of total 382 units. The concrete structure (RCC) is 6% complete.

Read full summary

Marathon Neovalley Narmada is a BMC-sanctioned project by M/S Nexzone Fiscal Services Pvt Ltd in Bhandup West, Mumbai 400078, registered with MahaRERA as 2 phases (P51800050264, P51800081112). The first phase was launched in March 2023. Together the phases have 382 units in 2 buildings: 360 homes (1 RK, 1 BHK and 2 BHK) and 22 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA.

The phases' registered possession dates run from December 2027 to December 2029; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 6% complete and final finishes 0% complete. Neither phase has its structure complete.

306 units booked out of total 382 units (80%). Since the July 2026 update, 103 more units have been booked.