Courtyard, Santacruz East

by Royal Minerva Realty LLP · Santacruz East, Mumbai 400098 · Map

Launched
Apr 20234 yrs 11 mths promised
Possession (MahaRERA)
Mar 2028Not extended
Concrete structure
90%Mid-construction
Booked
94 of 11582% · 86 in Jul 2026
Buildings
41.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
7
2 BHK
67
3 BHK
41
Total units
115
Buildings
4
Land
1.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)90%
Finishes, lifts and services75%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 55%Dec 2025: Concrete structure (RCC) 70%Jul 2026: Concrete structure (RCC) 88%Oct 2026: Concrete structure (RCC) 90%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 75%Oct 2026: Final finishes 75%Excavation 100%Concrete structure (RCC) 90%Final finishes 75%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%75%94
100%88%75%86
100%70%0%62
100%55%0%23

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Courtyard by Royal Minerva Realty LLP is a 115-unit BMC-sanctioned project in Santacruz East, Mumbai 400098, launched in April 2023 with possession due in March 2028. 94 units booked out of total 115 units. The concrete structure (RCC) is 90% complete.

Read full summary

Courtyard is a BMC-sanctioned project by Royal Minerva Realty LLP in Santacruz East, Mumbai 400098, registered with MahaRERA as P51800050456. It was launched in April 2023. It has 115 units in 4 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is March 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 90% complete, final finishes 75% complete.

94 units booked out of total 115 units (82%). Since the July 2026 update, 8 more units have been booked and the reported concrete structure (RCC) has gone from 88% to 90%.