Modispaces Amizarna, Malad West
Ready to move
by Modispaces Real Estate Pvt Ltd · Malad West, Mumbai 400064 · Map
- Launched
- Apr 20232 yrs 8 mths originally promised
- Possession (MahaRERA)
- Mar 2027Extended by 1 yr 3 mths
- Concrete structure
- 100%Ready to move
- Booked
- 7 of 2330%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 10
- 2 BHK
- 13
- Total units
- 23
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 7 | |
| 100% | 100% | 100% | – | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | 7 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400064
Projects with 10–50 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 8 mths | 2 yrs 2 mths |
| Possession date extended | By 1 yr 3 mths | 1 of 3 |
| Possession date (MahaRERA) | Mar 2027 | Dec 2026 |
| Concrete structure (RCC) | 100% | 60% |
| Units booked | 30% | 39% |
| MahaRERA complaints (filed by or against the builder) | 0 | 1 |
The 3 projects
- Jaymala Sadan Chsl, Malad West
- Malad Webb, Malad West
- Trishul Co-Operative Housing Society Ltd, Malad West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Jaymala Sadan Chsl | March 2023 | December 2026 | 11% | 13 units booked out of total 33 units |
| Malad Webb | September 2023 | April 2028 | 80% | 3 units booked out of 13 units for sale |
| Trishul Co-Operative Housing Society Ltd | October 2023 | December 2025 | 60% | 14 units booked out of 17 units for sale |
About this project
Modispaces Amizarna by Modispaces Real Estate Pvt Ltd is a 23-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in April 2023 with possession due in March 2027. 7 units booked out of total 23 units. The concrete structure (RCC) is complete.
Read full summary
Modispaces Amizarna is a BMC-sanctioned project by Modispaces Real Estate Pvt Ltd in Malad West, Mumbai 400064, registered with MahaRERA as P51800050579. It was launched in April 2023. It has 23 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is March 2027, extended by 1 year 3 months from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
7 units booked out of total 23 units (30%).