Skip to main content

Devtaa Pratham, Goregaon West

by Vipul Mitra Co-Operative Housing Society · Goregaon West, Mumbai 400062 · Map

Launched
Apr 20233 yrs 8 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
21 of 2584% · 34 rehab units
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale21 booked out of 25 units

Rehab34 units for existing members

Total 59 units. Rehab units are not for sale.

Project facts

2 BHK
30
3 BHK
29
Total units
59
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
25
Rehab units
34

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services20%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 40%Dec 2025: Concrete structure (RCC) 70%Jul 2026: Concrete structure (RCC) 80%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 20%Jul 2026: Final finishes 20%Oct 2026: Final finishes 20%Excavation 100%Concrete structure (RCC) 100%Final finishes 20%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%20%21
100%80%20%19
100%70%20%15
100%40%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Devtaa Pratham by Vipul Mitra Co-Operative Housing Society is a 59-unit BMC-sanctioned project in Goregaon West, Mumbai 400062, launched in April 2023 with possession due in December 2026. 21 units booked out of 25 units for sale. The concrete structure (RCC) is complete.

Read full summary

Devtaa Pratham is a BMC-sanctioned project by Vipul Mitra Co-Operative Housing Society in Goregaon West, Mumbai 400062, registered with MahaRERA as P51800050716. It was launched in April 2023. It has 59 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 59 units, 25 are for sale and 34 are rehab units for existing members.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 20% complete.

21 units booked out of 25 units for sale (84%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 80% to 100%.