Marquis Residences, Malad West

by Embassy Enterprises · Malad West, Mumbai 400064 · Map

Launched
May 2023First of 2 phases
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
100%Weighted across 2 phases
Booked
44 of 15429% · 37 in Jul 2026
Buildings
30.9 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
18
2 BHK
84
3 BHK
27
4 BHK
15
Other units
10
Total units
154
Buildings
3
Land
0.9 acres
Phases
2
MahaRERA complaints
0

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Marquis Residences Phase 1
Completed
P518000508000100%30%
Marquis Residences Phase 2
Nearing possession
P51800051092144100%28%
Show updates by phase

Marquis Residences Phase 1 (P51800050800)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%3
100%100%100%3
100%100%100%5
100%100%80%4

"–" means MahaRERA shows no figure for that update.

Marquis Residences Phase 2 (P51800051092)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%63%41
100%100%18%34
100%100%5%23
100%38%0%19

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services65%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 42%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 5%Dec 2025: Final finishes 11%Jul 2026: Final finishes 23%Oct 2026: Final finishes 65%Excavation 100%Concrete structure (RCC) 100%Final finishes 65%

How to read construction stages

Compared with 4 similar projects in PIN 400064

Projects with 70–300 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 1 mth3 yrs 9 mths
Possession date extendedNo2 of 4
Possession date (MahaRERA)Dec 2028Dec 2027
Concrete structure (RCC)100%50%
Units booked29%46%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Marquis Residences by Embassy Enterprises is a 154-unit BMC-sanctioned project in Malad West, Mumbai 400064, registered with MahaRERA in 2 phases, with possession due in December 2028. 44 units booked out of total 154 units. The concrete structure (RCC) is complete.

Read full summary

Marquis Residences is a BMC-sanctioned project by Embassy Enterprises in Malad West, Mumbai 400064, registered with MahaRERA as 2 phases (P51800050800, P51800051092). The first phase was launched in May 2023. Together the phases have 154 units in 3 buildings: 144 homes (1, 2, 3 and 4 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 1 is completed and 1 is active.

The registered possession date is December 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 65% complete. Both phases have their structure complete.

44 units booked out of total 154 units (29%). Since the July 2026 update, 7 more units have been booked.